OriginalCanesCanesCanes
All-ACC (#1 most reproted porster on CIS)
- Joined
- Feb 7, 2013
- Messages
- 35,725
Hasn’t been the same since the kitchen contracting job @Tad Footeball ‘s place.
Hasn’t been the same since the kitchen contracting job @Tad Footeball ‘s place.
I AM A ROBOT
GOCANES
***** the coaches offices, the full occupancy certification, the interior designers's color coordinated furniture -
I just wanna know one thing!
What about the Ice-ee/snowball machine?
Is it delivered, and is it plumbed and wired?
001 0110 111 1010 0011”
GOCANES
I see you’ve plugged in your cornball machine
I ALSO AM A ROBOT.
CIS going down hill ... having nothing to do with me
If you'll resort to just reading - and no posting - you'll immediately note an elevation in topic material discussions.
That could be YOUR contribution to improving CIS.
Somebody needs a snowcone
You too?
So, do I need to be worried? Are all the change orders for the no-dead-spot-verbal alarm-system-in-case-of-*******-harakiri in place now?
ICANEDOIT,
I know I said I would just watch but there are some here that really want honest updates here's another one ready.
I just received rev. #6 worth $10,000.00 for a couple additional panel boards, copper bus mounting straps for existing switch boards,additional 400 amp 65 kaic rated sensitron breaker ,solid core ct meter sensor, external SPD 100 ka TVS, 45 KVA xfrmr and 9 position meter racks.
Figure and estimated 4 weeks for manufacturing and 3-4 days shipping common carrier, keep in mind this is ONLY the electrical side , plumbing ,HVAC and so on has there revisions also to deal with.
Just sharing with everyone.
GOCANES
So when you saying they will be able to use the field to practice?ICANEDOIT,
I know I said I would just watch but there are some here that really want honest updates here's another one ready.
I just received rev. #6 worth $10,000.00 for a couple additional panel boards, copper bus mounting straps for existing switch boards,additional 400 amp 65 kaic rated sensitron breaker ,solid core ct meter sensor, external SPD 100 ka TVS, 45 KVA xfrmr and 9 position meter racks.
Figure and estimated 4 weeks for manufacturing and 3-4 days shipping common carrier, keep in mind this is ONLY the electrical side , plumbing ,HVAC and so on has there revisions also to deal with.
Just sharing with everyone.
GOCANES