Indoor Practice Field

Advertisement
design/permitting - 4~5 months depending on development regs
construction - 7~12 months depending on bells & whistles
 
You can get an IPF done in less than a year if it's done fast. But with South Florida construction probably will take 2 years..
 
Advertisement
design/permitting - 4~5 months depending on development regs
construction - 7~12 months depending on bells & whistles

The city of Coral Gables is the worst city when it comes to permits. They will take longer than 4-5 months.
 
what do you all think, 9 months? Break ground in December and ready for fall camp next year? the new braves and falcons stadiums have gone up pretty quickly, so this should be less than a baby, no?
 